Business Park more than 50 percent complete

Print
Font Size:
Default font size
Larger font size

Posted: Thursday, March 27, 2014 2:58 pm

COPPERAS COVE — The Narrows Business and Technology Park is more than 50 percent complete even after an unexpected $22,000 change order to the Copperas Cove Economic Development Corporation project.

The change order removed another foot of soil from the future Charles Tillman Way, that will cut through the park. The unplanned work brings the cost of developing the land to $1.58 million.

“This will increase the bill,” said Polo Enriquez, the corporation’s executive director. But it won’t be delaying the project.

While the project is not yet 50 percent billed, the development is more than half finished, said project engineer Otto Wiederhold with Walker Partners.

Read more in tomorrow’s Killeen Daily Herald.

More about

More about

More about

Rules of Conduct

  • 1 Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
  • 2 Don't Threaten or Abuse. Threats of harming another person will not be tolerated. AND PLEASE TURN OFF CAPS LOCK.
  • 3 Be Truthful. Don't knowingly lie about anyone or anything.
  • 4 Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
  • 5 Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
  • 6 Share with Us. We'd love to hear eyewitness accounts, the history behind an article.

Welcome to the discussion.